Assume that the delivered lines of code L of a software is related to the effort E in person months and duration t in calendar months by the relation L P* (E/B)1/3 * t4/3, where P and B are two constants for the software process and skills factor. For a software project, the effort was estimated to be 20 person months and the duration was estimated to be 8 months. However, the customer asked the project team to complete the software project in 4 months. What would be the required effort in person months?

  1. 10
  2. 40
  3. 160
  4. 320
in IS&Software Engineering retagged by
3.1k views

2 Answers

6 votes
6 votes
Best answer

P* (E1/B)1/3 * t14/3 = P* (E2/B)1/3 * t24/3

E1 = 20 person-months

t1 = 8 months

t2 = 4 months

On calculation we get E2 = 320 person-months (So, D is the answer)

edited by

1 comment

yes (D) in correct.

And I got it Exactly 320 ,NOT nearest :P

4
4
0 votes
0 votes

Ans is D 320

 

Answer:

Related questions

Quick search syntax
tags tag:apple
author user:martin
title title:apple
content content:apple
exclude -tag:apple
force match +apple
views views:100
score score:10
answers answers:2
is accepted isaccepted:true
is closed isclosed:true