Consider a software project with the following information domain characteristic for calculation of function point metric.

Number of external inputs $(I)=30$

Number of external output$(O)=60$

Number of external inquiries $(E)=23$

Number of files $(F)=08$

Number of external interfaces $(N)=02$

It is given that the complexity weighting factors for $\text{I, O, E, F and N}$ are $\text{4, 5, 4, 10 and 7}$, respectively. It is also given that, out of fourteen value adjustment factors that influence the development effort, four factors are not applicable, each of the other four factors have value $3$, and each of the remaining factors have value $4$. The computed value of function point metric is __________

  1. $612.06$
  2. $212.05$
  3. $305.09$
  4. $806.9$