Software Cost Performance index (CPI) is given by :

  1. $\large \frac{BCWP}{ACWP}$
  2.  
  3. BCWP-ACWP
  4. BCWP-BCWS

 

Where : $\begin{array}{l}\text{BCWP stands for Budgeted Cost of Work Performed} \\ \text{BCWS stands for Budget Cost of Work Scheduled} \\ \text{ACWP stands for Actual Cost of Work Performed}\end{array}$

 

in IS&Software Engineering edited by
865 views

1 Answer

0 votes
0 votes

Correct Answer: 

(a) CPI= BCWP/ACWP

Cost performance index (CPI): The ratio of budgeted costs to actual costs (BCWP/ACWP) and CPI is often
used to predict the magnitude of a possible cost overrun.

 

Reference: Chandramouli Subramanian, Saikat Dutt, Chandramouli Seetharaman, B. G. Geetha-Software Engineering- Person Education

edited by

Related questions

Quick search syntax
tags tag:apple
author user:martin
title title:apple
content content:apple
exclude -tag:apple
force match +apple
views views:100
score score:10
answers answers:2
is accepted isaccepted:true
is closed isclosed:true