400 views

1 Answer

Related questions

2 votes
2 votes
1 answer
1
Kapil asked Sep 29, 2016
976 views
Check whether the given schedule is conflict serializable or not ? R2(A); R3(C); W3(A); W2(A); W2(B); W3(C); R1(A); R1(B); W1(A); W1(B)
0 votes
0 votes
1 answer
2
3 votes
3 votes
2 answers
3
reena_kandari asked Jul 22, 2017
7,453 views
How to check if a schedule is allowed in 2PL or not?S1:R2(A)W1(B)W1(C)R3(B)R2(B)R1(A)R2(C)W3(A)S2:W2(A)W1(A)W3(A)W2(B)W1(B)W3(B)
1 votes
1 votes
3 answers
4
learncp asked Sep 18, 2015
1,514 views
Suppose we have a schedule containing two transactions  as shown-$\begin{bmatrix} T1 & T2 \\ R(A) & \\ W(A) & \\ & R(A) \\  & W(A) \\ R(B)& \\ W(B)& \\ & R(B) \\  & W(...