When working alone A, B and C can complete a piece of work in 10, 15 and 20 days respectively. At the most only two people can work on each day and nobody works more than two consecutive days. What is the minimum number of days that they will take to finish the work?

  1.   6 days
  2.   6(2/3) days
  3.   6(4/5)days
in Quantitative Aptitude
1.7k views

1 Answer

0 votes
0 votes
Option C) 6(4/5) days

2 Comments

please give a soltuion..
0
0
No one works for 2 consecutive days means we can allow A B and C to work like following
First day A and B works Second day A+C works and third day B+C works and then again the cycle goes

So in three days days they complete (13/30) part of work done
Next 3 days Total work done = 26/30 part

Remaining 1-(26/30) = (4/30) part

A and B takes (4/5 ) time to complete it
So 3+3+4/5 = 6(4/5) days
2
2
Quick search syntax
tags tag:apple
author user:martin
title title:apple
content content:apple
exclude -tag:apple
force match +apple
views views:100
score score:10
answers answers:2
is accepted isaccepted:true
is closed isclosed:true