Which of the following is correct ? I.Two phase locking is an optimistic protocol. II. Two phase locking is pessimistic protocol III. Time stamping is an optimistic protocol. IV. Time stamping is pessimistic protocol.

A

I and III

B

II and IV

C

I and IV

D

II and III

in Databases
by
1.2k views

1 Answer

0 votes
0 votes
validation protocol is optimistic protocol while locking and timestamps are pessimistic protocols.

so ii and iv. are correct.