in IS&Software Engineering recategorized by
350 views
1 vote
1 vote

Consider a software development project with seven tasks T1-T7.

Activity

Duration

Dependence

T1

3

-

T2

2

T1

T3

3

T2

T4

5

T1

T5

2

T3,T4

T6

4

T3,T4

T7

5

T3,T4

 

If developer A is available from the start of the project and developer B and C become available after three weeks of the start of the project. Schedule the project and show your results in the form of a bar chart and resource histogram.

 

in IS&Software Engineering recategorized by
by
350 views

Please log in or register to answer this question.