Which of the following is not included in the waterfall model?
Waterfall model does not have iteration or feedback path.
Requirement Gathering,Design,Coding is there for waterfall model. But no risk analysis. Bcz once done ;we r not doing the iterative action.whatever Done is Done ;).. So Ans is B. Risk Analysis https://en.m.wikipedia.org/wiki/Waterfall_model
Option B. is Correct Answer